Construction Updates

Construction Updates
(Aug 11, 2010)

Beginning tomorrow, August 12, the contractor, Northwest Earthmovers Inc., and their subcontractors, will begin road reconstruction work on existing Saltzman Road, between 128th Terrace and Filbert Street with the goal to have the road within this segment substantially completed prior to the Labor Day weekend.

The following is the tentative schedule for the resurfacing work, weather dependent:

August 12 and 13:

The week of August 16:

The week of August 23:

NOTE: Because there will be several days between the initial pulverization of the existing roadway and the installation of the first lift of asphalt, traffic will need to be run on the base rock. Measures will be in place to minimize dust and to caution drivers in this section of the roadway.

As with most construction activities, there will be noise, dust, and traffic impacts. The County apologizes in advance for these inconveniences and appreciate your understanding and patience.

Work Hours: 7:00 am - 5:00 pm Monday thru Friday

Lane Restrictions: 9:00 am - 3:30 pm Monday thru Friday

Washington County Project Page

 

For more information, contact:
Matt Costigan, Engineering Project Manager
matthew_costigan@co.washington.or.us or (503) 846-7825